联系电话: 186-6568-2076

国营G船厂与荷兰F公司船舶建造合同纠纷

来源:原创 作者:杨超男律师 浏览: 时间:2018-09-14

G船厂与荷兰F公司在2010年5月18日签订了两艘半潜船的造船合同。订单签订后,G船厂通过分包异地建造。因受金融危机的影响,船东出现资信变动、拖欠进度款甚至可能弃船的风险。我们协助G公司与船东谈判,就拖欠1#船交船款、2#船出坞款问题,与船东签订书面备忘,明确船东付款违约的事实。同时,协助船厂为船东提供融资渠道,最终由中国银行、中信保为船东提供短期融资。G船厂顺利将1#船交付并收到交船款,2#船的出坞款也顺利收回。

Shipbuilding contract dispute between State-owned Shipyard G and F Company of Netherlands.

G Shipyard and F company of Netherlands came into a shipbuilding contract for two semi-submersible ships on May 18, 2010. After the order was signed, G Shipyard subcontracted the project to another shipyard. Due to the impact of the financial crisis, the owner was at risk of credit, delayed the payment and even willing to cancel the shipbuilding contract. We assisted G Company in negotiating with the owner, signed a written memo with the owner on the issue of delayed payment of delivery of 1# ship and docking of 2# ship, and clarifying the fact that the owner was in default. At the same time, we assisted the shipyard in providing financing channels for the owner. Ultimately Bank of China and CITIC Insurance provided short-term financing for the owner. G Shipyard successfully delivered the 1# ship and received the payment of delivery of 1# ship and docking of 2# ship.

免责声明:本网部分文章和信息来源于国际互联网,本网转载出于传递更多信息和学习之目的。如转载稿涉及版权等问题,请立即联系网站所有人,我们会给与以更改或者删除相关文章,维护您的权利。